Management company name
Industrial Park «Rodniki» LLC
Taxpayer Personal Identification Number (INN) of Management company
3703021585
Website of industrial park
ip-rodniki.ru
National management standart GOST R 56301-2014 "Industrial parks. Requirements
Yes
Accreditation with the Ministry of Industry and Trade of Russia
No
Land plot
Total area of industrial park, hectares
90,4 ha
Available area of industrial park for residents allocation, hectares
44 ha
Permitted use of land plots in the industrial park
104
Permissible hazard class for companies, structures and other facilities to be located
V
Legal grounds for the management company s disposal of the industrial park territory
Agency agreement
Production properties
Available area of industrial park manufacturing buildings/premises, square meters
70000 m2
Maximum ceiling height of industrial premises, meters
12 m
The presence of a crane beam
No
Storage area, square meters
0 m2
Office areas, square meters
5700 m2
Average rental price for manufacturing buildings/premises, rub./m2 per year
1416 rub/m2 per year
Total area of industrial park manufacturing buildings/premises, square meters
300000 m2
Park Infrastructure
Existing connection of industrial park to road
Asphalt
Connection of industrial park to the railway
Yes
Parking for cargo vehicles on the territory of the industrial park
Yes
Electricity (power) supply
Yes
Total electricity (power) capacity, MW
50 MW
Free available electricity (power) supply capacity, MW
43 MW
Electricity supply source
Own generation
Name of grid company
собственная ТЭЦ мощностью 17 МВт, собственная электроподстанция мощностью 50 МВт
The cost of connecting to the power grid on the territory of industrial parks residents, rub/MW
0 rub/MW
Average electricity tariff for industrial enterprises in the industrial park, rub/kWh
0 rub./kWh
Total gas supply capacity, cubic meters/hour
9470 m3/h
Available gas supply capacity, cubic meters/hour
2000 m3/h
Gas supply tariff, cubic meters/hour
0 rub/m3
Total heating supply capacity, gigacalories/hour
100 Gcal / h
Free available heating supply, gigacalories/hour
25 Gcal / h
Heat supply tariff, rub/gigacalories
0 rub/Gcal
Total water supply capacity, cubic meters/hour
1200 m3/h
Available water supply capacity, cubic meters/hour
400 m3/h
Water supply source
Private water intake facility
Water supply tariff
0 rub/m3
Total sewage system capacity, cubic meters/hour
0 m3/h
Availability of treatment facilities
Yes
Connection to external wastewater disposal systems
No
Benefits and Government Support
Preferential treatment for businesses
TOSER